SRINAGAR, AUGUST 29 (KNO) : Secretary PHE, I&FC, Farooq Ahmed Shah today called upon the engineers of the Flood Control Department to increase their visibility on ground and take proactive initiatives to achieve set goals for flood protection works in the State. The Secretary issued these directions while chairing a high-level meeting to review the functioning of Flood Mitigation plans here today.

The meeting was attended by the Chief Engineer I&FC, M. M Shahnawaz, Director, Disaster Management Amir Ali, Ex- Chief Engineers, Experts, Superintendent Engineers, Executive Engineers of I&FC department and officers of allied departments. The meeting was informed that in 1st phase, Rs 399.29 crore flood recovery project was taken up under Prime Ministers Development Package (PMDP). It was informed that the Ist phase of dredging and de-silting of River Jhelum will be completed by March 2019.

It was disclosed that out of Rs 399.29 crore, an amount of Rs 142.33 crore has been paid as land compensation of Flood Spill Channel (FSC) at Shariefabad and Naidkhai, Rs 82.00 crore for Re-Sectioning of FSC, while Rs 35 crore have been expended for construction of two bridges on FSC at Shariefabad and Naidkhai. With regard to dredging of River Jhelum in various stretches, Rs 46 crore has been spent so far, while as Rs 73 crore for flood protection works on River Jehlum and vulnerable spots from Khannabal to Baramulla and Rs 20.96 crore have been spent on other project sub-heads.

The Secretary was informed that the amount has been spent on the works pertaining to flood protection, anti-erosion, widening of the river, raising of embankments, re-sectioning, de-silting and dredging of the river under the flood management plan. He also directed officials to ensure zero tolerance of encroachments on the banks of FSC, Jhelum and other water bodies. He said that if any officer is found delaying the removal of encroachments, strict action will be taken against the officials. He said that any defaulter contractor or the contractor working not upto the mark will face cancellation of their allotted tenders.

He said that the projects are of utmost importance and Governor Administration is personally monitoring the project. He said these works once finished will greatly reduce the risks of flood in the coming years. The meeting was informed that 2nd phase of dredging amounting to Rs. 1684 Cr will start very soon for which survey is under process through web cost sponsored by government. The Secretary said that Governor Administration is keen to provide liberal funding for these projects. He said that dredging unit in Baramulla will be revived.

For the purpose, the Secretary said two dredgers machines will be purchased soon, and tenders in this regard have already been finalized. Men and machinery will work 24x7, employees will be given trainings for driving of dredgers, added Farooq. The meeting also discussed about the proposal to connect Anchar lake with Sindh nallah is in pipeline. The Secretary also directed concerned officers to start de-silting work of Chunt Khul on war footing basis, for which the SOPs put in place by the LAWDA have been discussed threadbare.

To deal with any kind of flood threat in future, the Secretary impressed for keeping field staff and JCB Machinery ready. The meeting also decided to prepare a proposal for the construction of Seasonally Small Dams near rivers for preserving of water. On the occasion, Director Disaster Management, Ex- Chief Engineers and Experts of flood control gave their valuable suggestions to protect valley from the floods in future.

Trending

TOP STORIES8 hours ago

Terrorist associate arrested with arms, ammunition in Bandipora: Police | KNO

TOP STORIES22 hours ago

Don’t repeat 1987 rigged election in Kashmir: Parra to Govt | KNO

TOP STORIES22 hours ago

Over 3 lakh tourists visit Pahalgam in last four months | KNO

TOP STORIES23 hours ago

Sajad Lone extends gratitude to J&K Pahari Cultural & Welfare Forum | KNO

TOP STORIES23 hours ago

2 terrorist associates held in Shopian: Police | KNO

TOP STORIES23 hours ago

Basantgarh Encounter Case: One suspect arrested for providing logistic support to terrorists | KNO

TOP STORIES23 hours ago

66-Day Hunger Strike for Ladakh Statehood Ends Ahead of Lok Sabha Elections | KNO

TOP STORIES23 hours ago

Kashmiri Pandit votes hold key amid tough triangular contest in Srinagar LS seat | KNO

TOP STORIES23 hours ago

Students to benefit from DYD program: VC CUS | KNO

TOP STORIES23 hours ago

Speed up work on City's Khayam road to prevent traffic congestion, locals urge authorities | KNO

TOP STORIES23 hours ago

18 ‘Pink Polling Stations’ established for female voters: CEO J&K | KNO

TOP STORIES23 hours ago

Campaigning for Srinagar LS seat ends | KNO

TOP STORIES23 hours ago

Campaigning ends, Srinagar LS seat set for showdown on Monday | KNO

TOP STORIES1 days ago

BJP holds crucial meeting of Srinagar cadre, decides to vote against NC, PDP, Congress in LS polls | KNO

TOP STORIES1 days ago

ECI SOPs mandate curbs under section 114 for last 72, 48 hours: DC Pulwama | KNO

TOP STORIES1 days ago

Speedy tempo vehicle crushes 60 sheep to death, injures 40 in Kulgam | KNO

TOP STORIES1 days ago

Sajad Lone gets EC notice over MCC violation | KNO

Copyright © 2021